TeraWulf Secures Google Credit Support for $19 Billion Anthropic Data Center Lease

TeraWulf ($WULF) has secured credit support from Alphabet ($GOOGL) for debt financing tied to its previously announced $19 billion, 20-year Anthropic lease at the Justified Data Campus in Kentucky.
Google's backing strengthens the project's financing profile and could help TeraWulf obtain more competitive long-term borrowing terms. The $19 billion represents contracted lease commitments, not the amount of financing provided by Google.
Separately, TeraWulf signed a definitive construction agreement with Fluor ($FLR) covering three data center buildings at the campus. Phased ready-for-service completions are scheduled to begin in late 2027 and continue through Q2 2028.
TeraWulf also recently expanded its contracted power capacity to 1 GW at the Muskie Data Campus in eastern Kentucky.